GM Plant to Save Money by Capturing Rainwater

Published by in Business

GM Plant to Save Money by Capturing Rainwater

GM Plant to Save Money by Capturing Rainwater

General Motor's plant will reuse captured rainwater for manufacturing processes throughout the 4-million-square-foot facility.

UNvOtT9.jpgEnvironmental managers are increasing looking to improve water management and efficiency to save money and resources now — and in the future.

The UN projects a 40 percent water supply shortfall globally by 2030 and this represents a $63 trillion risk to business and communities, according to CDP (formerly Carbon Disclosure Project).

Going about implementing water conservation projects, however, can seem daunting. Using recycled water, for example, can save millions of gallons annually but can be difficult due to funding and infrastructure challenges.

But through collaboration, both internally and externally, as well as creative thinking, companies can conserve water and save money, as General Motors’ new project to capture stormwater illustrates.

On its company blog, GM describes the GM Detroit-Hamtramck Assembly project, two years in the making, and says it will save the plant nearly $2 million annually.

It will also save water: the plant will reuse captured rainwater for manufacturing processes throughout the 4-million-square-foot facility.

“In one application, stormwater is pumped to an onsite power house where it is treated, fed through existing sand filters and then used in the plant’s cooling towers,” Al Hildreth, GM global energy manager, told Environmental Leader. “This process alone eliminates over 20 percent of the plant’s water usage and saves over $140,000 annually.”

PART_1464949967186_20160531_135318.jpgHildreth says the initial goal of the project was to avoid stormwater discharge fees from the city of Detroit.

The plant had two retention ponds onsite, but paid fees to send excess stormwater to a city treatment plant. “These fees made up 14 percent of the entire plant’s utility budget,” Hildreth said.

The solution? Build a third pond on the facility’s grounds.

In the third quarter of 2014, GM dug up more than 20,000 dump truck loads of dirt and created a third pond with a maximum retention capacity of 47 million gallons of water at one time, the equivalent of a 100-year storm event.

GM expects to see a return on investment in a little over a year.

“This two-year project took just under $3 million to complete,” Hildreth said. “The biggest expense was to dig a new pond, install interconnections between the ponds and storm sewer, and build a supply line to the power house. We also installed a new pumping system, carbon filtration tank and pumps, and refurbished and rerouted pipes.”

As the blog explains, the system works like this:

Source: Environmental Leader

Tags

Category: Business

1 Comment

Glad to see they are using rainwater,but collecting off the roof and storing in tanks is much more efficient and is easier to clean. A step in the right direction. Using rainwater is niot reuse, because the water has never been used before. Greywater is reuse.

Using rainwater as a stormwater solution saves on both ends.

 

 

Published by

Permalink