How to start building your own desalination plant?

Published on by in Technology

First step is to define the plant capacity. Plants with capacities above 45-50 ML/D are all custom-designed. Its engineering starts from FEED – front end engineering and design. It may be requested from Crenger here.  

http://www.crenger.com/requestfeed.html

For capacities below 40 ML/D Crenger recommends off-the-shelf modular containerized SWRO units.
To purchase them one needs a technical specification. It may by easily prepared even with zero experience with the following free web application.

http://www.crenger.com/gbe/servlet/rfqgenerator