Successful launch of first Dragon Class tidal powerplant in Vestmanna, Faroe IslandsMinesto has now successfully completed the first week of com...
Published on by Water Network Research, Official research team of The Water Network
Minesto has now successfully completed the first week of commissioning, including satisfactory electricity production and verification of all core functionalities with the new Dragon 4 tidal power plant. The kite has generated first electricity to grid "right out of the box" and the commissioning plan has been executed as planned.