What you need to know about a $3.86B Metro Vancouver wastewater treatment plant | CBC News

Published on by in Market Info

What you need to know about a $3.86B Metro Vancouver wastewater treatment plant | CBC News

New North Shore plant 4 years behind schedule with building costs well over original estimate

Chad Pawson · CBC News · Posted: Jun 15, 2024 8:00 AM EDT | Last Updated: June 15

Construction workers are pictured working on the North Shore Wastewater Treatment Plant in North Vancouver Vancouver, B.C., on Friday, June 14, 2024.

Construction workers are pictured working on the North Shore Wastewater treatment plant in North Vancouver, B.C., on June 14, 2024. (Ben Nelms/CBC News)

A new wastewater treatment plant under construction in B.C.'s most populated region is four years beyond its original completion date and more than five times over budget.

Here's what's important to know about it.

The project

The North Shore Wastewater treatment plant was first announced in 2011 as a $700 million project to replace the existing Lions Gate plant, which is one of the last on the West Coast of North America to provide only primary wastewater treatment, meaning it only removes waste from water that floats or sinks.

There are five wastewater treatment plants across Metro Vancouver, in five separate sewerage areas. Collectively, they process more than one billion litres of wastewater produced by the region's nearly 2.5 million residents.

Currently, the new North Shore plant, located at the corner of West 1st Street and Phillip Avenue, is only partially built. When completed, it will serve more than 300,000 residents and businesses in the Districts of North and West Vancouver, the City of North Vancouver along with the Squamish and Tsleil-Waututh Nations.

It's needed partly to meet Metro Vancouver's growing population, but also to comply with federal regulations announced in 2012 that require municipalities to do secondary wastewater treatment, where dissolved organic material is removed.

Problems

After it was announced in 2011, there was very little attention given to the project. Ten years later, the regional government, Metro Vancouver, publicly shared details of a conflict with the contractor working on the project, Acciona Wastewater Solutions LP.

In September of that year, Acciona laid off the majority of its workers at the project site amid accusations from Metro Vancouver that it was not honouring its contract obligations.

A construction site picture rebar and concrete structures.

The North Shore Wastewater treatment plant in North Vancouver, B.C., pictured here on June 14, 2024, was first announced in 2011 as a $700 million project. The estimated cost for the new plant has grown to $3.86 billion. (Ben Nelms/CBC News)

The regional government said the completion date would be pushed back to 2023. The new budget for the project was more than $1 billion.

Contractor terminated

In October 2021, Metro Vancouver terminated the contract with Acciona over long construction delays and a rising price tag for the project. It said the new plant, despite being three years late, was only 36 per cent complete.

For its part Acciona said it was committed to finishing the project, but was dealing with unforeseen challenges such as design changes to the project it alleged Metro Vancouver demanded.

The acrimony led to legal action involving the two sides. Acciona is trying to recover $250 million in damages and unpaid bills, while Metro Vancouver said Acciona signed fixed-price and fixed-date contracts, and despite revisions to the agreed timeline, failed to meet key construction milestones. 

As the suit plays out in court, Metro Vancouver said it's "confident" its decision to terminate was justified.

Metro Vancouver has since hired PCL Constructors Westcoast Inc. and designer AECOM to take over the project, while it seeks a new contractor to complete it.

More costs

In March of this year though came the biggest news over the project: an even higher price tag of $3.86 billion.

A Metro Vancouver Board task force determined the higher cost by taking into account inflation of construction and labour costs, work that was needed to address design and construction deficiencies for the project and how other large infrastructure projects were competing for the same resources.

"The reality is, the cost to deliver the program has changed significantly since its initial estimate 13 years ago," , Commissioner and CAO of Metro Vancouver Jerry Dobrovolny said in a statement at the time.

Taxpayers pay more

Attached link

https://www.cbc.ca/news/canada/british-columbia/what-you-need-to-know-north-shore-wastewater-treatment-plant-1.7235368

Taxonomy