SMART Strom Water Tunnel Malaysia

Published on by in Technology

SMART Strom Water Tunnel Malaysia

The World's Longest Multi-Purpose Tunnel

The main objective of this tunnel is to solve the problem of flash floods in Kuala Lumpur and also to reduce traffic jams along Jalan Sungai Besi and Loke Yew flyover at Pudu during rush hour. There are two components of this tunnel, the stormwater tunnel and motorway tunnel. It is the longest multi-purpose tunnel in the world.

In 2011, the SMART tunnel received the UN Habitat Scroll of Honour Award for its innovative and unique management of storm water and peak hour traffic.

It begins at Kampung Berembang lake near Klang River at Ampang and ends at Taman Desa lake near Kerayong River at Salak South. The project is led by the government, including Malaysian Highway Authority (Lembaga Lebuhraya Malaysia = LLM) and the Department of Irrigation and Drainage Malaysia (Jabatan Pengairan dan Saliran = JPS) and also a company joint venture pact between Gamuda Berhad and Malaysian Mining Corporation Berhad (MMC).

In 2001 the Government sought proposals for a solution that would allow a typical flood of three to six hours' duration to occur without flooding the city centre. A tunnel that would allow floods to bypass the centre was one way of achieving this, providing it was coupled with temporary storage facilities to keep flows downstream of Kuala Lumpur within the capacity of the river channel. A group led by Gamuda engaged SSP, a large Malaysian consultant engineering firm, and Mott MacDonald UK to develop proposals for a tunnel with holding ponds at upstream anddownstream ends of the tunnel.

Construction of the tunnel began in 25 November 2003. Two Herrenknecht's Tunnel Boring Machines (TBM) from Germany were used, including "Tuah" on north side and "Gemilang" on south side. Gusztáv Klados was the senior project manager of the project.
On 11 December 2003, the 13.2 m diameter Mixshield TBM, Tuah, completed a 737 m section after 24 weeks of excavation. By the end of January 2004, Tuah would start a second drive covering a distance of 4.5 km to Kampung Berembang lake. The motorway sections on the SMART system was officially opened at 3:00PM, 14 May 2007, after multiple delays.
Meanwhile, the stormwater sections on the SMART system began operations at the end of January 2007.

As of July 18, 2010 the SMART system has prevented seven potentially disastrous flash floods in the city centre, having entered its first mode 3 operation only weeks after the opening of the motorway.

The first mode, under normal conditions where there is no storm, no flood water will be diverted into the system. When the second mode is activated, flood water is diverted into the bypass tunnel in the lower channel of the motorway tunnel. The motorway section is still open to traffic at this stage. When the third mode is in operation, the motorway will be closed to all traffic. After making sure all vehicles have exited the motorway, automated water-tight gates will be opened to allow flood waters to pass through. The motorway will be reopened to traffic within 48 hours of closure.

Source: SpiesLeaks