Published by Harry Beyer, Principal Water Engineer
Hey Mark,
The way this usually works is that proposals are made against a detailed project requirements brief. You will not get good offers with a few lines of requirements. There are too many unknowns: financing; land ownership; regulatory approvals; stakeholder approvals; raw water availability; level of service - quality, quantity, target asset life, metering, billing ; etc. Unless you have someone very experienced, you will need professional help just to put a brief together for starters which could easily take a year and cost a few $M. If you don't do that there is a very high risk the community won't get the outcome they expect and the final cost will be far in excess of what it should be.
Best regards, Harry